Brownfield FAQs

< Return to all categories

Part 2 Proposal

FAQ-BSP-28
Q: Is it acceptable for Bidders to not submit a Bid on Bid Date for one or more of the Projects for which a Bidder provided bid assurance collateral?

It is acceptable to not submit a Bid on Bid Date for one or more of the Projects for which a Bidder provided bid assurance collateral. There is no penalty for not submitting a Bid. If a Bid is not submitted for a Project, that Project will not be considered in selecting the winning Projects.

07-25-2019

FAQ-BSP-20
Q: Our Project has qualified pursuant to a successful Part 1 Proposal. Is it possible to amend the Project size? The Project does not have a signed interconnection agreement.

For a Project that does not have a signed interconnection agreement, the Procurement Administrator will allow a change in this regard in limited circumstances, namely if:

  • The site control documentation as submitted with the Part 1 Proposal is sufficient to support the changed size of the Project;
  • The Officer of the Seller resubmits the representations required by the P1 Project Certifications Insert (#P1-4); and
  • The Bidder submits sufficient bid assurance collateral to support the increased size of the Project as necessary.

The Procurement Administrator requires notice of the Seller’s desire to change the Project size no later than five (5) business days prior to the Bid Date and the Procurement Administrator will determine whether such a change can be allowed at that time.

07-02-2019

FAQ-BSP-10
Q: Where can I find the inserts to the online Part 1 and Part 2 Forms for the Brownfield RFP?

On June 13, 2019, the Procurement Administrator posted the inserts to the online Part 1 and Part 2 Forms to the Final Materials page of the Brownfield section of the procurement website under the heading “Summer 2019 Brownfield RFP Documents”.

06-14-2019