IFP-55: The bid assurance collateral for a Company is a certain amount per MW up to a maximum. If we are presenting multiple Projects, does the maximum apply to each Project separately or does the maximum apply to the aggregate size across all Projects?

The amount of bid assurance collateral should be calculated on the basis of the aggregate size of all Projects presented by a Bidder.  The maximum on the bid assurance collateral applies to the aggregate size of all Projects.