The Procurement Administrator issued the draft Brownfield REC Contract on May 23, 2019. A redline of this draft to the final REC contract under the Fall 2018 Brownfield and Utility-Scale Solar RFP was also posted at that time. In addition to several clarifications, the changes were to make the contract only applicable to new photovoltaic projects that are built on brownfield sites, to incorporate additional force majeure events to Article 6, and to remove fax as a delivery method for notices and other correspondence. Please review the documents posted for complete details.
Preliminary Proposal documents will be posted by June 3 and the final RFP documents will be posted by June 13, 2019. The Procurement Administrator will hold a webcast on June 13 and will discuss any changes from the prior procurement events. The documents will be posted to the dedicated Brownfield Site Photovoltaic Procurement page of the procurement website.
If you have not done so already, please RSVP for the webcast.