The contracts under the 2017-2018 Initial Forward Procurements, which encompasses the Summer 2017 Wind and Solar RFP and the two procurement events under the Spring 2018 New Solar RFP, are for a 15 year term. The second procurement event under the Spring 2018 New Solar RFP will begin with a webcast on Thursday, March 29, 2018. Additional information is available on the New Solar tab of the procurement website.
Prior to these procurements, the Illinois Power Agency held a long-term renewable energy procurement in 2010 for 20-year contracts. Additional information on this RFP is available here: