DG-26: Can a project be interconnected at a location that does not currently have a metered customer?

With its Part 1 Proposal for the DG RFP, a Bidder is required to certify that the system is located, or will be located when installed, on the customer side of a Customer’s electric meter and the system is, or will be primarily used to offset that customer’s electricity load.  This requirement implies that the Customer and the system must be located on the same site (and thus the requirements of the DG RFP are not met by “virtual net metering” or by the resale of electricity from the system to a Customer in a location other than the location of the system).