BEC-3: Can bidders provide comments on the Pre-Bid Letters of Credit for the Spring 2018 Block Energy and Capacity RFP?

No. A Bidder may only provide comments on or propose modifications to the changes that have been made to the Standard Pre-Bid Letter of Credit for a procurement event for a Company relative to the previously used Standard Pre-Bid Letter of Credit. The Procurement Administrator will not solicit comments on the Standard Pre-Bid Letter of Credit when such changes are limited to these administrative updates: (i) expiration date, date of the procurement event, and dates of the supply period; (ii) docket number; or (iii) contact information for the Company. The changes that have been made to the Standard Pre-Bid Letters of Credit are administrative only and, as such, the Procurement Administrator will not be soliciting comments on the Standard Pre-Bid Letters of Credit.