No. Under the REC Contract, there is a requirement for at least one REC to be delivered by June 1, 2021, which shall not be excused by Force Majeure. Failure to deliver at least one REC by June 1, 2021 under any circumstance, including delays in the interconnection process, constitutes an Event of Default under the REC Contract.