Announcements


W&S-22: Can we use RECs issued prior to the contract execution to meet the Delivery Year Requirements during the Delivery Term?

Only RECs based on electricity generated during the Delivery Term and 2 months prior to the start of the Delivery Term would be eligible for delivery during the Delivery Term as such term is defined in the REC Contract.