35: Can you clarify how the Procurement Administrator will notify a Bidder that fails to satisfy all the requirements of the Part 2 Proposal? Paragraph VI.1.7 seems to refer to the Procurement Administrator returning originals of the Part 2 Form and supporting documents.

If a Bidder fails to satisfy all the requirements of the Part 2 Proposal, the Procurement Administrator will send a notice to that effect via email only. The notice will list the information that was not received from the Bidder.  The references to originals of the Part 2 Form and supporting documents no longer apply since the Part 2 Proposal is submitted online.