IFP-36: Can you confirm that we are not required to submit any materials for our project if we intend on participating only in the second procurement event under the New Solar RFP?

That is correct. The Part 1 Window for the second procurement event opens on March 30, 2018 and nothing is required before that time if a Bidder is considering participation in the second procurement event only.

However, we will note that if you do elect to submit materials in the first procurement event for a Project and the Project is qualified pursuant to the submission of the online Part 1 Form and all required documents, then if you wish to present the same Project in the second procurement event, you can do so simply by resubmitting the online Part 1 Form without changes during the Part 1 Window for the second procurement event.