IFP-29: Can you post a redline of the final REC Contract (posted February 6, 2018) to the draft REC Contract (posted January 12, 2018)?

A redline comparison was not posted as there were no changes made between the draft REC Contract (posted January 12, 2018) and final REC Contract (posted February 6, 2018). A redline of the draft REC Contract to the REC Contract used in the 2017 Wind and Solar procurement event is posted to the Draft Documents page of the New Solar tab of the procurement website.