C2S-4: Can you provide an estimate of the Supplier Fee ($/REC) and instructions for payment to the IPA?

Proponents and Sellers are required to pay the Supplier Fee to the Illinois Power Agency (“IPA”) for a Project that has been selected through the C2S Procurement and approved by the Commission no later than seven (7) business days after ICC approval of the results of the procurement event.  An estimate of the Supplier Fee is $1.00 times the annual quantity of RECs selected for a Project.  The final amount of the Supplier Fee (in $/REC) and instructions regarding payment of the Supplier Fee will be provided no later than 6 PM CPT on Monday, April 25, 2022.