CRG-5: Could we split a single wind turbine into two “co-located” community renewables projects? I ask because we are considering a wind turbine with a capacity that is over 2 MW.

No. That would be inconsistent with the definition of a community renewable generation project in Section 1-10 of the Illinois Power Agency Act:

“Community renewable generation project” means an electric generating facility that:

[items (1) – (3) omitted]

(4) is limited in nameplate capacity to less than or equal to 2,000 kilowatts.