W&S-48: Do bidders commit to a firm in-service date for a project? How is the start of the delivery term determined?

There is no commitment to a particular in-service date required of the bidder.  Please note, however, that the Date of First Operation of the Project cannot be on or before June 1, 2017 and that at least one REC must be delivered from the Project by June 1, 2021.  The delivery term under the REC Contract begins the later of June 1, 2019 and the date at which the first REC from the Project is issued by PJM EIS GATS or M-RETS.

Revised 8-01-2017 first posted 6-28-2017