Announcements


CRG-18: Do co-located projects count as a single project for purposes of bid assurance collateral?

The amount of bid assurance collateral required for the Projects presented by a Bidder is determined separately for each Project and each Company as detailed below:

  • The amount of bid assurance collateral required for AIC is $10,000 per Project.
  • The amount of bid assurance collateral required for ComEd is $20,000 per Project.

Each co-located Project counts as a separate “Project” for purposes of calculating the amount of bid assurance  collateral.