SPV-42: Do we have to indicate the Bid price in the Part 1 Window or the Part 2 Window?

No, the Bid price cannot and need not be submitted in Part 1 Window or Part 2 Window of the RFP process. A Bid in the SPV RFP is the price at which the Seller offers to supply a REC of a product, and a bidder is not required to submit this price until the Bid Date.