Announcements


S&B-21: Do you provide any guidance on the contents of documents used to fulfill the requirements related to demonstrating site control?

On August 30, 2018, the Procurement Administrator posted Appendix 4 – Minimum Requirements for Letter of Intent, Memorandum of Understanding, or Other Document to the dedicated Brownfield and Utility-Scale Solar Draft Documents page. This document lists the documentation that may be used to fulfill this requirement and the minimum requirements should a Seller or Bidder choose to develop its own document that meets its business needs. Additional information will be provided in the RFP Documents, which will posted no later than Tuesday, October 16, 2018.