WND-3: Does the definition of Force Majeure only include a delay associated with processing a permit request, or does it also include the denial of a permit request?

The definition of Force Majeure in the Winter 2021 Utility-Scale Wind Final REC Agreement includes delays associated with processing of permit requests, provided that Seller can demonstrate to Buyer and the IPA that such delay is not primarily attributable to the Seller’s failure to make in a timely manner permitting requests. The denial of a permit request is not included in the definition of Force Majeure.