Announcements


BE-1: Have the requirements for participating in the Block Energy / Standard Products RFP been established? Are these the same for all procurement events and RFPs?

The requirements for participating in the procurement events under the 2017 Illinois Power Agency Procurement Plan differ depending on the procurement event type. The requirements for a procurement event are stated in the RFP Rules for that procurement event. The DRAFT RFP Rules for the Block Energy/Standard Products RFP are available here:

https://www.ipa-energyrfp.com/spring-block-energy/draft-documents/

Final RFP documents are expected to be released on March 7, 2017. If you are inquiring about another RFP, please submit a follow-up question.