The description can be a few words or a short paragraph. The Bidder should first indicate whether an application for interconnection has been made. If it has, the Bidder indicates the utility or Regional Transmission Organization (“RTO”, i.e., PJM or MISO) to which the Seller has applied and the Bidder can state which of the utility’s/RTO’s milestones for interconnection the Project has met. If an application for interconnection has not yet been made, the Bidder can indicate the utility or RTO to which the application is expected to be made and provide any other milestones in the development of the Project that have been reached to date. For brownfield site photovoltaic projects, the Bidder additionally describes the status of remediation of the site.