Announcements


BEC-14: I have a prior version of the Pre-Bid Letters of Credit instructions from a prior procurement event. Is the update to this document available for the BEC RFP?

The update to this document is scheduled to be provided to Bidders with the Part 1 Notification, which will be sent no later than April 8, 2019.  The Procurement Administrator takes your question as a request for early issuance of this document.  This document will be available by Monday April 1 upon request to the Procurement Administrator and will be sent to you as soon as it becomes available.