WND-46: I see the optional changes to the Guaranty in Contract Insert #P2-5 for ComEd only. Does that meant that AIC and MEC will not accept changes to the Guaranty?

The lists of optional changes to the (AIC) Form of Guaranty and the (MEC) Form of Guaranty are available under the FINAL Fall 2018 Wind REC Contract header on the Final Materials page of the procurement website. These do not appear in the Contract Insert because the Guarantor prepares the guaranty for AIC and MEC (while ComEd prepares the guaranty for the ComEd REC Contract).