Capacity-4: I understand that there could be a payment adjustment on delivered ZRCs under the (AIC) Capacity Agreement if the ZRCs are not from the compliance zone. Is this payment adjustment based on distance from the Compliance Zone (LRZ 4)?

The payment adjustment is based on the difference between the Auction Clearing Price from the MISO Planning Resource Auction (“PRA”) for the Source Zone associated with the ZRCs and the Compliance Zone (LRZ 4). Please see FAQ-Capacity-1 and FAQ-Capacity-2 for examples of the payment adjustment.