The Collateral Requirement is posted upon contract execution in an amount of 1/15th of Maximum Contract Value under the applicable supplier contract(s) and remains in place throughout the term of the contract. Under the REC Contract, a Seller can request an extension as described in 5. Energization of the Project. However, if the Project is not built, the Collateral Requirement will be forfeited.