IFP-39: If a Project received a partial award, can the nameplate capacity of the Project be modified?

The obligations of the REC Contract are linked to the REC delivery and not to the size of the Project. However, if the project is not a brownfield site photovoltaic project, the RECs delivered under the terms of the REC Contract must be associated with generation from a utility-scale solar project, which is defined in the Act as having a nameplate capacity greater than 2,000 kW (AC rating).