Announcements


S&B-38: If the permit that we provide as documentation to demonstrate that the site is regulated by the IEPA Solid Waste Program is insufficient, will we be notified during the Part 1 Window?

Yes, generally if your Part 1 Proposal is incomplete or requires clarification, the Procurement Administrator will send a deficiency notice to the Bidder. If the permit provided is insufficient, the Procurement Administrator will provide an explanation and request additional information in that notice. A Bidder is generally given until the Part 1 Date or two (2) business days to respond to a first deficiency notice.