The answer depends on if the Bidder has changed. Should you present one or more projects under the Brownfield and Utility-Scale Solar RFP and the Bidder is unchanged, you are not required to pay the Bid Participation Fee in this RFP. If the Bidder changed since the prior 2018 procurement event, however, you will be required to pay the Bid Participation Fee again in this RFP.