S&B-45: If we already paid the Bid Participation Fee pursuant to participation in a prior 2018 procurement event, but we are participating as a different Bidder, are we required to pay the fee again?

If the Bidder changed since the prior 2018 procurement event you will be required to pay the Bid Participation Fee again in this RFP even if the Legal Name of Seller remains the same. If the Bidder is presenting Proposals for multiple Projects under the Brownfield and Utility-Scale Solar RFP, the Bidder is only required to pay a single Bid Participation Fee no matter how many Sellers are named.