If an Interconnection Agreement has not been fully executed for the Project, you are required to provide each Owner’s legal name and contact information as well as to provide documentation that you have control of the Project site. If you have a lease for the Project site, you have control of the Project site but you do not have ownership of the Project site. You are expected then: (i) to provide in the Owners Insert the legal name and contact information of the entity or individual with whom you have entered into the lease and that has ownership of the Project site; (ii) to provide a copy of the executed lease agreement or easement between you and the Owner or Owners. If there are multiple Owners of the Project site, you must provide documentation for Owners that together control at least 50% of the Project site.