Announcements


STP-9: Is a previously qualified bidder able to provide updated information in its Part 1 Proposal and still participate in the abbreviated qualification process?

In preparing the Part 1 Proposal, any previously qualified Bidder can use the abbreviated process. Through the abbreviated process, it is expected and required that a Bidder would submit any and all updates to the previously provided information. These updates will NOT result in a rejection of the Part 1 Proposal. By submitting the Part 1 Form without providing any updates, a Bidder is certifying that all previously provided information remains valid.