DG-34: Is a system that was bid as an identified system in the first round, but not selected as a winning system able to be identified as a system using RECS that were bid speculatively?

We understand you to be asking whether one of the systems that you name to the IPA to fulfill a forecast quantity can be an identified system that was not selected as part of the evaluation in the procurement event. Yes, this would be acceptable for winners of the June 2015 procurement event. A winning Bidder of forecast RECs in the Spring 2015 SPV has six months after the procurement event (October 16, 2015) to identify the system to the IPA.

For future procurement events, please consult the documents for that procurement event for additional timing requirements for providing an identified system after winning an award for a forecast quantity.