A project located in a COOP region can qualify to participate in the Indexed REC RFP. Such a project must meet the requirements in Sections IV and V of the Indexed REC RFP Rules. Please note, any Brownfield Site Photovoltaic Project must meet such definition in Section 1.9 of the Indexed REC Contract and be located in Illinois, and any Utility-Scale Wind or Utility-Scale Solar Projects must meet such definitions in Section 1.107 and 1.108 of the Indexed REC Contract and be located in Illinois or an adjacent state.
In addition, please see Indexed REC FAQs 16 and 5 for additional information.