BE-38: Is it possible that some of a Bidder’s Bids in the AIC Capacity procurement event are identified as “winning Bids” to the ICC, while others are not? For instance, if a Bidder submits Bids at the same price in $/MW-Day, is it the case that the Procurement Administrator accepts either all of the Bids or none of the Bids?

It is possible that only a portion of a Bidder’s Bids are accepted should the Bidder submit Bids for multiple ZRCs at the highest accepted price in order to exactly fill the ZRC Target for the Planning Year.