You must meet all requirements of the Part 1 Proposal, including any listed in the Second Item of Section 1 of the Part 1 Proposal, Participation in MISO or PJM Markets, by the Part 1 Date. Please note that Bidders who are currently a Seller to a Company under an applicable supplier contract or have been a Seller to a Company under an applicable supplier contract pursuant to a 2016, 2017, or 2018 procurement event under the BEC RFP or under the Standard Products RFP are exempt from the requirement listed in the Second Item of Section 1 of the Part 1 Proposal.