Yes. However, please note that under the terms of the SPV RFP, for a forecast quantity, the Seller must identify systems: (i) NO EARLIER than twenty (20) business days after the Bid Date or the first day of the quarter following the Bid Date, whichever comes last; and (ii) no later than six (6) months of the Bid Date.