CRG-22: Is the bid assurance collateral due on the Part 2 Date or on the Bid Date?

The Part 2 Proposal consists of the completed online Part 2 Form, the submission of bid assurance collateral, the submission of any other document required by the online Part 2 Form, and the bids. Only the bids are submitted on the Bid Date of December 13, 2019.  All other portions of the Part 2 Proposal, including the bid assurance collateral, must be received by 12 PM (noon) on the Part 2 Date, which is Wednesday, December 4, 2019.  Please see Paragraph VI.1.18 of the RFP Rules.