Announcements


W&S-2: Is the contract form subject to approval by the Illinois Commerce Commission (“ICC”)?

As required under Section 16-111.5 of the Public Utilities Act (through Section 1-75(c)(1)(G)(v) of the IPA Act), the Procurement Administrator develops the contracts in consultation with each of the applicable utilities, the Illinois Power Agency, the ICC Staff, and the Procurement Monitor. Only if these parties are unable to come to a consensus would the ICC then make a determination on the final contract form.