DG-98: Is the entity named as the Bidder in the Part 1 Proposal required to also be the entity that would sign the applicable supplier contracts if the Bidder has bids approved by the Commission?

Yes. With respect to signing the applicable supplier contracts, the entity named as the Bidder in the Part 1 Proposal must be the party that executes the applicable supplier contracts if the Bidder has bids approved by the Commission.