There is no process for “withdrawing” a Project from a procurement event under the RFP Rules. There is no penalty for not submitting materials for the Part 2 Proposal for a Project. If a Bidder submitted Part 1 Proposals for multiple Projects and does not submit a Part 2 Proposal for one of those Projects, then the amount of bid assurance collateral required with the Part 2 Proposal must be sufficient given the size of any Project(s) for which the Bidder is submitting a Part 2 Proposal.