If a Bidder does not have projects that are selected by the evaluation and for which bids are approved by the Commission, the bid assurance collateral will be returned after the Commission decision on the procurement event (December 2019). If the Bidder has projects that are selected by the evaluation for which bids are approved by the Commission, the bid assurance collateral will be returned once the Bidder executes the REC Contracts, pays the supplier fees, and posts any required Collateral Requirement under the terms of the REC Contracts (by February 2020).