W&S-107: My understanding is that under Public Act 099-0906, there is a 2% carve-out for brownfield site photovoltaic projects for the program overall. What is the specific carve-out for brownfield site photovoltaic projects within the Target of 200,000 RECs?

For purposes of the initial forward procurement, there is no carve-out for brownfield site photovoltaic projects.  The first procurement event Target of 200,000 RECs is thus for brownfield site photovoltaic projects and utility-scale solar projects combined, each of which is eligible to participate in this procurement process under Section 1-75(c)(1)(G)(ii) of the IPA Act.  Both types of projects are evaluated together on the basis of price alone.

You are correct that there is a 2% requirement for brownfield site photovoltaic projects in the Illinois RPS (20 ILCS 3855/1-75(c)(1)(C)).  Depending on the results of the initial forward procurements, the IPA will adjust future targets through procurements proposed in its long-term renewable resources procurement plan, currently under development, to meet that 2% brownfield site photovoltaic requirement.  Thus, if brownfield site photovoltaic projects are selected through the initial forward procurements in a manner that exceeds the 2% requirement, then the future targets for brownfield site photovoltaic projects will be set lower than they otherwise would have been (and vice versa with future targets representing more than the 2% overall requirement if less than this percentage is procured through the initial forward procurements) for future procurements proposed in the IPA’s long-term renewable resources procurement plan.