SPV-69: On the online Part 1 Form, it appears that it is only possible to submit one number for the forecast quantity of RECs. However, the rules and the illustrative bid form indicate that it is possible to submit multiple Bids for forecast quantities at different price points. Should the forecast quantity on the Part 1 Form simply be the total quantity to be bid, which would then be further described and broken out on the Bid Form?

Your understanding is correct. In the Part 1 Form, you are only required to indicate the number of forecast quantity of RECs you intend to bid.