W&S-68: Other than the deadline in which projects must deliver their first REC before June 2021, will suppliers be required to submit a date in which the first REC will be delivered, or can REC delivery start at any point between June 2019 and June 2021 with limited notice as to when the first REC is delivered?

Suppliers will not be required to submit a date at which the first REC will be delivered. However, suppliers do not have complete flexibility to start deliveries in the June 2019 to June 2021 window.  The Delivery Term under the terms of the REC Contract begins on the later of June 1, 2019 and the date at which the first REC is issued by PJM EIS GATS or M-RETS for the project regardless of when the initial date of REC delivery occurs. Once the Delivery Term starts, the supplier must comply with the delivery obligations under the REC Contract.