W&S-74: Prior procurement events have assumed a capacity factor of 14.38% when calculating RECs produced by a solar system. Is there a similar capacity factor associated with this event or are there no capacity factor assumptions?

There is no capacity factor pre-designated for the Wind and Solar RFP. A participant in the RFP will provide the annual quantity of RECs that the project will deliver under the terms of the REC Contract as part of its bid.