DG-149: Should the bid assurance collateral be sent to the Companies (AIC and ComEd but not MEC)?

The bid assurance collateral must be in the form of a Letter of Credit with the IPA as beneficiary. Bid assurance collateral is NOT sent to the Companies that are purchasing through this procurement event. It is correct that AIC and ComEd but not MEC are purchasing RECs through this procurement event.