Announcements


BEC-18: Suppose we win in the upcoming AIC Capacity procurement event. Can you confirm that the due date for supplier contracts to be fully executed is Monday, September 17, 2018 as stated in the calendar posted to the RFP website?

Yes. The due date for supplier contracts to be fully executed by winners in the upcoming AIC Capacity procurement event is Monday, September 17, 2018.