LIP-69: The capacity factor that we provided in the Part 1 Proposal is not longer valid. What is the procedure to update this information?

If any information provided in the Part 1 Proposal for a Project changes or any previous certification fails to remain valid you must notify the Procurement Administrator.  In the case of the capacity factor for a Project, please advise the Procurement Administrator of the new capacity factor, please provide your calculation of the annual number of RECs from the Project using this capacity factor, and please request that the Procurement Administrator re-issue your Bid Form.  Any such notice to the Procurement Administrator related to the capacity factor must be made no later than two business days prior to the Bid Date.