That is correct. The Bid Assurance Collateral in the draft Part 2 Proposal requirements requires providing a letter of credit to each utility in an amount that is based on the size of the project presented ($5,000/MW for wind, $15,000/MW for solar projects, subject to a $25,000 minimum). The final requirements are expected to be posted on July 19, 2017.