SPV-189: The SPV Rules state that a system must be no more than 2,000 kW in size. Could this requirement be lifted in a future procurement event for RECs of distributed generation systems to allow for systems larger than 2,000 kW?

To be considered distributed generation, a system must, among other requirements, be no more than 2,000 kW in size.  To the extent that a future procurement event solicits RECs from distributed generation systems, this requirement would remain.