DG-80: We are planning to develop a system in the Large Size Class and there is one complication. The roof needs repairs before the system is installed. Can we still include the system in our Proposal? What are the deadlines for the system to be operational?

If you include this system in your Proposal, and the system becomes part of bids approved by the Commission, you will be required to complete the registration of the system in GATS or M-RETS and for the initial meter read date as recorded in GATS and M-RETS to occur by May 31, 2018. If you include this system in your Proposal, it would be considered a “new” system.